Well-to-topside slug-control replay

This public synthetic replay covers the NeqSim #5036 wellhead choke, 5.4 km flowline/riser and three-phase inlet-separator case. It compares a fixed 58% wellhead-choke opening with a bounded liquid-level controller while retaining the same sinusoidal supply-pressure input and the same separator pressure, total-liquid and oil/water-interface loops.

Reproduction contract

The coarse-mesh 90 s receipt requires less than 2% difference in mean production between the cases, a lower regulated liquid peak, pipe phase-mass residual below 1e-8 kg, and complete sampled series for choke opening, riser liquid rate, separator pressure, total liquid level and oil/water interface.

Metric (analysis window) Open loop Regulated Relative change
Mean production (kg/s) 18.0989 17.9198 -0.99%
Peak riser liquid rate (kg/s) 14.4430 13.2260 -8.43%
Separator pressure range (bar) 2.3742 1.7804 -25.01%
Total-liquid level range (m) 0.01920 0.01759 -8.39%
Oil/water-interface range (m) 0.00497 0.00658 +32.43%
Maximum pipe phase residual (kg) 2.50e-11 3.21e-11 —

The water-interface excursion is an explicit tradeoff in this controller configuration. It is reported rather than hidden by retuning the common separator loops independently between cases. The complete series contains 91 samples per mode. The MCP replay completed in 67.8 s on the qualification host.

Boundary qualification

The riser outlet remains at the exact qualified pressure, 56.40099362 bara. The separator pressure controller is centred on the same target. Feeding the live separator pressure back through TwoFluidPipe.setOutletPressure is not claimed as qualified by this study: millibar-scale repeated changes can suppress liquid through-flow even though each individual boundary value is valid. That route needs a separate moving-pressure-boundary qualification; enforcing a nonnegative outlet sign is not a substitute.

This is a deterministic numerical reference study. It is not experimental or field validation, and it does not establish commercial simulator parity.

Two wells and a platform inlet choke

The production restart decision study places the choke between the riser and the separator. It adds pressure-dependent well inflow, a live separator pressure boundary, recompression with recycle, fluid alternatives, withheld refinements and a field-history comparison. The original wellhead-choke replay remains available through runPipeline. Its quantityEvidence response records the mesh, requested timestep, prescribed outlet boundary, accepted pipe phase residual, peak riser liquid rate and mean inlet production for each control mode. A single call performs no cross-mesh comparison. The rates use kg/s and the residual uses kg.