Monte Carlo Risk Simulation

Monte Carlo simulation provides probabilistic production forecasts by randomly sampling equipment failure events over a time horizon.


Overview

Traditional deterministic analysis uses single-point estimates:

Monte Carlo provides probability distributions:


Mathematical Foundation

Stochastic Failure Model

Equipment failures are modeled as a Poisson process with exponential inter-arrival times.

Time to next failure:

\[T_f \sim \text{Exponential}(\lambda)\] \[f(t) = \lambda e^{-\lambda t}, \quad t \geq 0\]

Where $\lambda$ is the failure rate (failures per hour).

Mean time to failure:

\[E[T_f] = \frac{1}{\lambda} = \text{MTTF}\]

Sampling algorithm:

\[T_f = -\frac{1}{\lambda} \ln(U), \quad U \sim \text{Uniform}(0,1)\]

Repair Time Model

Repair times are modeled as exponential (or can be extended to log-normal):

\[T_r \sim \text{Exponential}(\mu)\]

Where $\mu = 1/\text{MTTR}$.

Production Calculation

For each time step $t$:

\[P(t) = P_{\text{design}} \times \prod_{i \in \text{operating}} C_{f,i}(t)\]

Where:

Cumulative Production

\[P_{\text{total}} = \int_0^T P(t) \, dt \approx \sum_{t=0}^{T} P(t) \Delta t\]

Simulation Algorithm

Algorithm: Monte Carlo Production Simulation
─────────────────────────────────────────────
Input: Equipment list with (λ, MTTR, capacity_factor)
       Simulation horizon T (days)
       Number of iterations N

For each iteration i = 1 to N:
    Initialize: all equipment OPERATING
    cumulative_production = 0
    
    For each hour t = 0 to T × 24:
        For each equipment e:
            If e is OPERATING:
                Sample U ~ Uniform(0,1)
                If U < λ_e × Δt:
                    e.state = FAILED
                    e.repair_remaining = sample_repair_time(MTTR_e)
            
            If e is FAILED:
                e.repair_remaining -= Δt
                If e.repair_remaining <= 0:
                    e.state = OPERATING
        
        # Calculate production this hour
        capacity = 1.0
        For each equipment e:
            If e is FAILED:
                capacity *= e.capacity_factor_when_failed
        
        production_this_hour = design_rate × capacity
        cumulative_production += production_this_hour
    
    Store result[i] = cumulative_production

Calculate statistics:
    P50 = median(results)
    P10 = percentile(results, 10)
    P90 = percentile(results, 90)
    Expected = mean(results)
    Availability = mean(uptimes) / total_time

Using OperationalRiskSimulator

Basic Usage

// Create simulator
OperationalRiskSimulator simulator = new OperationalRiskSimulator(processSystem);

// Configure streams for production measurement
simulator.setFeedStreamName("Well Feed");
simulator.setProductStreamName("Export Gas");

// Add equipment reliability data
// Parameters: name, failure rate (per year), MTTR (hours)
simulator.addEquipmentReliability("HP Compressor", 0.5, 24);
simulator.addEquipmentReliability("LP Compressor", 0.5, 24);
simulator.addEquipmentReliability("Export Pump", 0.2, 8);
simulator.addEquipmentReliability("Separator", 0.1, 4);

// Set random seed for reproducibility
simulator.setRandomSeed(42);

// Run simulation: 10,000 iterations, 365 days
OperationalRiskResult result = simulator.runSimulation(10000, 365);

Interpreting Results

// Production statistics
System.out.println("Expected production: " + result.getExpectedProduction() + " kg");
System.out.println("P10 production: " + result.getP10Production() + " kg");
System.out.println("P50 production: " + result.getP50Production() + " kg");
System.out.println("P90 production: " + result.getP90Production() + " kg");

// Availability
System.out.println("Expected availability: " + result.getAvailability() + "%");

// Downtime events
System.out.println("Expected downtime events: " + result.getExpectedDowntimeEvents());
System.out.println("Expected total downtime: " + result.getExpectedDowntimeHours() + " hours");

// Confidence interval
System.out.println("95% CI: [" + result.getLowerConfidenceLimit() + 
                   ", " + result.getUpperConfidenceLimit() + "]");

Percentile Interpretation

Percentile Meaning Use Case
P10 10% chance of exceeding Optimistic scenario
P50 50% chance of exceeding Most likely scenario
P90 90% chance of exceeding Conservative planning
Mean Expected (average) value Financial budgeting

Visual Example

Production Distribution (10,000 iterations)
───────────────────────────────────────────

        ▲ Frequency
        │
        │        ████
        │       ██████
        │      ████████
        │     ██████████
        │    ████████████
        │   ██████████████
        │  ████████████████
        │ ██████████████████
        ├──┬──┬──┬──┬──┬──┬──┬──► Production
           P10  P50 Mean P90

P10 = 88,000 tonnes (optimistic)
P50 = 95,000 tonnes (median)
Mean = 94,500 tonnes (expected)
P90 = 99,000 tonnes (conservative)

Advanced Configuration

Equipment-Specific Failure Modes

// Create custom failure mode
EquipmentFailureMode degradedMode = EquipmentFailureMode.builder()
    .name("Partial fouling")
    .type(FailureType.DEGRADED)
    .capacityFactor(0.7)  // 70% capacity when degraded
    .build();

// Add with custom failure mode
simulator.addEquipmentReliability("Heat Exchanger", 1.0, 48, degradedMode);

Correlated Failures

For common-cause failures (e.g., power outage affecting multiple equipment):

// Define correlation group
simulator.addCorrelatedFailureGroup(
    "Power System",
    Arrays.asList("Compressor A", "Compressor B", "Pump A"),
    0.05,  // 5% of failures are correlated
    4.0    // 4 hour common repair time
);

Seasonal Variation

// Vary production rate by season (e.g., gas demand)
Map<Integer, Double> seasonalFactors = new HashMap<>();
seasonalFactors.put(1, 1.2);   // January: 120%
seasonalFactors.put(7, 0.8);   // July: 80%
// ... other months

simulator.setSeasonalProductionFactors(seasonalFactors);

Convergence Analysis

Determining Iteration Count

The number of iterations $N$ affects result accuracy:

Standard error of mean:

\[SE = \frac{\sigma}{\sqrt{N}}\]

Required iterations for precision $\epsilon$:

\[N = \left(\frac{z \cdot \sigma}{\epsilon}\right)^2\]

Where $z = 1.96$ for 95% confidence.

Convergence Check

// Run with increasing iterations
int[] iterations = {100, 500, 1000, 5000, 10000};

for (int n : iterations) {
    OperationalRiskResult result = simulator.runSimulation(n, 365);
    System.out.printf("N=%d: P50=%.0f, StdErr=%.1f%n", 
        n, result.getP50Production(), result.getStandardError());
}

Typical output:

N=100: P50=94500, StdErr=2500
N=500: P50=94800, StdErr=1100
N=1000: P50=95100, StdErr=780
N=5000: P50=94950, StdErr=350
N=10000: P50=95000, StdErr=245

Rule of thumb: Use N ≥ 10,000 for financial decisions.


System Availability Calculation

Series System

For equipment in series (all must operate):

\[A_{\text{series}} = \prod_{i=1}^{n} A_i\]

Parallel System (Redundancy)

For k-out-of-n redundancy:

\[A_{\text{parallel}} = \sum_{i=k}^{n} \binom{n}{i} A^i (1-A)^{n-i}\]

For 1-out-of-2 (simple redundancy):

\[A_{\text{1oo2}} = 1 - (1-A_1)(1-A_2)\]

Example: Compressor System

// Two parallel compressors, each 99% available
double A_single = 0.99;
double A_parallel = 1 - Math.pow(1 - A_single, 2);  // 99.99%

// Three compressors, need 2 operating
int n = 3, k = 2;
double A_2oo3 = 0;
for (int i = k; i <= n; i++) {
    A_2oo3 += binomial(n, i) * Math.pow(A_single, i) * Math.pow(1-A_single, n-i);
}
// A_2oo3 ≈ 99.97%

Output Formats

Summary Statistics

String summary = result.getSummary();

Output:

═══════════════════════════════════════════════════════════
            MONTE CARLO SIMULATION RESULTS
═══════════════════════════════════════════════════════════
Iterations: 10,000
Horizon: 365 days
Random Seed: 42

PRODUCTION STATISTICS:
─────────────────────────────────────────────────────────
  Design Production:      100,000,000 kg
  Expected Production:     95,200,000 kg (95.2%)
  P10 Production:          98,500,000 kg
  P50 Production:          95,400,000 kg
  P90 Production:          91,200,000 kg
  Standard Deviation:       2,450,000 kg
  95% Confidence Interval: [94,900,000 - 95,500,000]

AVAILABILITY:
─────────────────────────────────────────────────────────
  Expected Availability:   96.2%
  Expected Downtime:       333 hours/year
  Expected Events:         3.2 failures/year

EQUIPMENT CONTRIBUTION TO DOWNTIME:
─────────────────────────────────────────────────────────
  HP Compressor:    145 hours (43.5%)
  LP Compressor:    142 hours (42.6%)
  Export Pump:       32 hours (9.6%)
  Separator:         14 hours (4.2%)
═══════════════════════════════════════════════════════════

JSON Export

String json = result.toJson();

Integration with Risk Matrix

Monte Carlo results can populate risk matrix probability categories:

// Get failure frequency from simulation
double compressorFailures = result.getEquipmentFailureCount("HP Compressor") / years;
ProbabilityCategory prob = ProbabilityCategory.fromFrequency(compressorFailures);

// Get consequence from production impact
double productionLoss = result.getProductionLossFromEquipment("HP Compressor");
ConsequenceCategory cons = ConsequenceCategory.fromProductionLoss(productionLoss);

// Add to risk matrix
riskMatrix.addRiskItem("HP Compressor", prob, cons, estimatedCost);

Best Practices

  1. Use sufficient iterations (≥10,000 for decisions)
  2. Set random seed for reproducibility
  3. Validate with historical data when available
  4. Include all significant failures (not just trips)
  5. Consider correlations between equipment
  6. Report confidence intervals, not just point estimates
  7. Sensitivity analysis on uncertain parameters