Introduction

The NeqSim Risk Simulation Framework provides comprehensive tools for analyzing equipment failures, their impact on production, and optimizing plant operation under degraded conditions. It integrates with NeqSim’s process simulation capabilities to provide physics-based risk assessment.


Key Concepts

1. Equipment Failure Modes

Equipment can fail in different ways, each with different consequences:

Failure Type Description Capacity Factor
TRIP Equipment stops completely 0%
DEGRADED Reduced capacity operation 10-90%
PARTIAL_FAILURE Some functions lost 20-80%
FULL_FAILURE Complete breakdown 0%
MAINTENANCE Planned shutdown 0%
BYPASSED Flow routed around 0% (for that unit)

2. Reliability Metrics

Standard reliability metrics from OREDA (Offshore Reliability Data):

Metric Symbol Description
Mean Time To Failure MTTF Average operating time before failure
Mean Time To Repair MTTR Average repair duration
Mean Time Between Failures MTBF MTTF + MTTR
Failure Rate λ Failures per time unit
Availability A Fraction of time operational

3. Risk Assessment

Risk is evaluated on two dimensions:

  1. Probability (likelihood of failure)
  2. Consequence (impact when failure occurs)

The combination determines the Risk Level:

Risk Level = f(Probability, Consequence)

4. Process Topology

Equipment connections form a directed graph:

Feed → Separator → Compressor → Cooler → Export
                 ↘ Pump → Storage

Understanding topology enables:


Framework Capabilities

✅ Equipment Failure Modeling

✅ Production Impact Analysis

✅ Monte Carlo Simulation

✅ Risk Matrix

✅ Topology Analysis

✅ STID Tagging

✅ Dependency Analysis


Portfolio risk analysis

The advanced framework’s P5 capability uses PortfolioRiskAnalyzer to aggregate asset availability losses and shared common-cause scenarios. Use it for production-loss screening, not as a safety acceptance or financial valuation model.

The input basis is maximum asset production in boe/day, an availability fraction from zero to one, scenario frequency in events/year, duration in days, and a fractional production impact for each affected asset. The simulation period is in years, with a 365-day year. Common-cause event counts are sampled from a Poisson distribution; their losses are added to the baseline availability losses.

PortfolioRiskResult reports production rates in boe/day and accumulated losses in boe over the simulation period. Its P10/P50/P90/P99 values are ascending loss percentiles: a higher percentile means a larger loss, not a higher production forecast. The value-at-risk accessor is a production-loss quantity, not monetary VaR.

The additive model does not reconcile overlapping outages or cap their combined loss at the available production. Reported portfolio availability is based on individual asset availability and does not deduct common-cause losses. Shared scenarios are not a general asset-correlation matrix. Validate the input basis, avoid double counting, and obtain independent engineering review before using these screening results for decisions. The portfolio regression tests show the implemented API and software checks; they are not independent field qualification.


Typical Workflow

1. Build Process Model
   └─► ProcessSystem with equipment

2. Define Failure Scenarios
   └─► EquipmentFailureMode for each critical unit

3. Assign Reliability Data
   └─► MTTF, MTTR from OREDA

4. Build Topology
   └─► ProcessTopologyAnalyzer.buildTopology()

5. Tag Equipment
   └─► STID functional locations

6. Analyze Dependencies
   └─► DependencyAnalyzer.analyzeFailure()

7. Build Risk Matrix
   └─► RiskMatrix.buildRiskMatrix()

8. Run Monte Carlo
   └─► OperationalRiskSimulator.runSimulation()

9. Optimize Degraded Operation
   └─► DegradedOperationOptimizer.optimize()

Industry Standards

This framework follows industry standards:

Standard Application
ISO 14224 Equipment taxonomy and reliability data
OREDA Offshore reliability data handbook
ISO 31000 Risk management principles
NORSOK Z-013 Risk and emergency preparedness
IEC 61508 Functional safety
API 580/581 Risk-based inspection

Mathematical Foundation

See Mathematical Reference for detailed formulas covering:


Next Steps