In this migration guide you will find:
- Information on date-input changes and constraints.
Migration overview
This doc guides you through migrating an existing eCalc™ model from the minor version v9.12 to v9.13.
We try to make this as easy as possible, and provide a step-by-step migration guide.
Main differences
- Enforce stricter rules for dates enforced
1. Enforce stricter rules for dates
The input dates within one file/resource must follow a common and accepted format. This ensures a mix of month-first and day-first cannot exist and cause misinterpretation. If time is present for one datapoint in file/resource, it must be included in all datapoints.
Accepted formats:
- ISO8601 — YYYY.MM.DD
- ISO8601 (with time) — YYYY.MM.DD HH:MM:SS
- Day-first — DD.MM.YYYY
- Day-first (with time) — DD.MM.YYYY HH:MM:SS
- Year only — YYYY
The change should not affect the getting of a model, but running updating and creating models/files should fail with a reasonable error message.